Explanation Of Scrum Burndown Charts – The Plotting, Requirement, And Purpose Of Burndown Charts

What is a burn down chart?


A burn down chart is an important tool in scrum. It provides a visual representation about the progress achieved in a sprint while it is underway. They are very common and extensively used by scrum masters while scrum is being implemented in a project. The quantity, or the amount of work remaining, in the form of pending tasks, is typically exhibited in a burn down chart. The chart is simple and easy to understand, even by people who are not familiar with scrum methodology. Burn down charts are very useful for estimation purposes, and are essential for determining the sprint velocity – the rate at which work in the form of user stories is being completed by the development team – and planning the sprint release.  

Plotting the burn down chart
A burn down chart can be plotted by including the work remaining in the form of story points along the vertical Y-axis and the working days along the horizontal X-axis. The pending work is typically represented in story points – a unit of measurement to calculate the importance and priority of user stories in the sprint backlog – instead of user stories. The reason is user stories are broken down into tasks during the second half of the sprint planning meeting by the development team. It becomes difficult to read and understand the chart if tasks are represented along the Y-axis. User stories are descriptive in nature, and do not have a number or a value associated with them, so it becomes difficult to estimate them. Therefore, the story points, which are numeric values associated with each user story, are used for plotting purposes. Know more on http://ezinearticles.com/?Explanation-Of-Scrum-Burndown-Charts---The-Plotting,-Requirement,-And-Purpose-Of-Burndown-Charts&id=8371905 

          "Please visit http://www.quickscrum.com to download the Quickscrum tool"  
  

No comments:

Post a Comment